Home > Company Information > Case Studies

Case Studies

Click the links below to view details of some of our recent projects

Case Study 1

Project: New Leisure Facility

Location: Bakewell, Derbyshire

Client: Balmoral Associates

Overview: A large area of ground was excavated to a depth of approximately eight metres to enable to construction of basement areas.

Maris Pumps Case Study - Pumping River Water

3 nr diesel units pumping away in line with one of our Settlement Tanks

Solution: As the river ran within 10 metres of the site, water was a major problem. This is where expertise of Maris Pumps Ltd came in. For the next eighteen months we worked closely with the client to keep the water at bay during this crucial time with between six to eight pumps coping with ingress 24/7.

top

 

Case Study 2

Project: Salvage Shipwrecks off the coast of Port Buchanan

Location: Liberia, West Africa

Client: Liberian Authorities

Overview: Our UK based client approached us with a requirement to remove water from a series of shipwrecks to enable salvage of the vessels.

Salvage Shipwrecks off the coast of Port Buchanan

Maris Pumps Ltd involved in cleaning up the beautiful Liberian coastline

Maris Pumps Ltd

Our selection of SPP Stirling units prior to shipment together with our client

Solution: As hire was not an option due to the distances involved, Maris Pumps Ltd put together a package for the sale of six diesel driven pump units and associated pipework

top

 

Case Study 3

Project: Removing Product from a Cement Plant

Location: Buxton, Derbyshire

Client: Tarmac

Overview: The need arose to transfer a large amount of sludge at short notice over a long distance from the plant to the lagoon

Removing Product from a Cement Plant

One of our engineers installing the pump and pipework

Solution: Due to the nature of the project and the distances to be covered, Maris Pumps Ltd employed one of our Pegson ‘High-Head’ Pumps complete with associated eight inch pipework.

The successful operation was completed over a two week period.

top

 

Case Study 4

Project: Fill a new section of canal

Location: Renishaw, Derbyshire

Client: R. B. Allfree & Co. Ltd

Overview: The need arose to fill a new section of the canal in an extremely limited time frame

Maris Pumps Ltd VS150 pump filling a new section of Renishaw Canal

One of our VS150 High Pressure Pumps working by Renishaw Canal.

Solution: We were tasked with the requirement to fill a new section of the canal in an extremely limited time frame. Our client requested around the clock operation and 24 hour support in order to meet their target time.

Using our knowledge and expertise, we rapidly responded by installing a 600 metre pipeline along with one of our VS150HP diesel driven units and completed the works within the allocated time slot promptly and efficiently.

top

 

Case Study 5

Project: To provide a complete stand-alone emergency flood alleviation package

Location: Nottinghamshire and surrounding areas

Client: Bassetlaw District Council

Maris Pumps Ltd emergency flood alleviation package

Our Sales Manager Richard Cutting together with the client

Solution: Maris Pumps Ltd prepared a proposal for the sale of a variety of pumping equipment to ensure that Bassetlaw District Council could provide emergency flood alleviation around the clock.

This package was largely composed of the sale of a new 4 inch rapid response diesel driven Pegson unit and a number of smaller units with associated hose and pipework.

top

 

Case Study 6

Project: Keeping fluid moving across roads & tracks during over pumping

Location: Construction Sites, Main Roads, Quarries, Power Stations, Sewage Works, etc

Overview: Maris Pumps Ltd identified the need to offer our clients the ability to continue pumping over roadways that cannot restrict vehicle access

Road Ramp™

The Road Ramp™ in action

Solution: To develop a ‘Road Ramp’ which offers a very low obstruction height without reducing the flow capability and avoiding blockages.

Introducing the patented Road Ramp™ complete with a 70 tonne weight limit.

Feedback from satisfied clients has suggested cost savings in reducing the need to bury pipes in the highway or erecting costly overhead gantries.

top